Two new warehouse buildings are rising on Old Pasco Road in Wesley Chapel, expanding an industrial park whose first announced tenant's space is back on the market.
Developer Rooker is erecting Buildings 2 and 4 at North Tampa 75, a business park south of Overpass Road and less than a mile from the I-75 interchange. A published site plan reviewed by Wesley Chapel Community shows the park's master plan calls for roughly 858,000 square feet of industrial space across four buildings.
Building 2, the largest at approximately 301,600 square feet, is under active construction. Contractor Catamount Constructors reported that concrete wall panels and steel structure were being erected, according to a construction update shared by Rooker. Building 4 is listed at 205,380 square feet.
Rooker has described Building 2 as speculative construction, meaning it is being built for leasing rather than for a specific occupant. Building 4 is a build-to-suit project for an unnamed repeat customer, according to the developer's public construction updates.
The Soule Co. question
The park's original Building 1, a 187,000-square-foot warehouse completed in 2023, was supposed to be fully leased.
On Oct. 30, 2024, the Pasco Economic Development Council announced that The Soule Co., a medical-products manufacturer, would occupy 127,820 square feet there. The company planned to hire 10 employees and invest $400,000 in racking systems and facility buildout, according to the announcement. The remaining 59,180 square feet had been leased to an unnamed Fortune 1,000 company in the heating, ventilation and air-conditioning (HVAC) industry.
That picture has changed. Rooker now lists the same 127,820-square-foot suite at 7594 Old Pasco Road as available Nov. 1, 2026. The listing does not explain why the space is on the market or whether The Soule Co. ever moved in.
Lindsey Osborne, president of The Soule Co., said in the 2024 Pasco EDC announcement that the company's goal was "to continue to grow in Pasco County …" The Soule Co. manufactures and packages medical supplies and had three Pasco County locations and 100 employees at the time of that announcement.
County investment and park history
The park traces to a 2019 Pasco County Commission vote approving a $3.7 million Penny for Pasco forgivable loan to Rooker. The developer closed on the 85-acre property in December 2021, according to the Pasco EDC announcement. John Rooker, CEO of Rooker, said in that announcement that county investments in infrastructure and a new I-75 interchange "are now attracting high quality employers to locate and grow in the area."
Rooker also advertises a 10-acre build-to-suit site within the park. The site plan shows a building of approximately 100,000 to 165,000 square feet could be accommodated there.
Road work nearing completion
Old Pasco Road itself has been under construction. A widening project covering the stretch from south of Sonny Drive to north of Overpass Road added two travel lanes, pedestrian improvements and new traffic signals at Lindenhurst Drive and a business-park entrance, the Laker/Lutz News reported in January 2024.
Pasco County said on Facebook that the road project was nearing completion, with northbound lanes being finished and final work underway on traffic signals, landscaping, storm drains and bus stop pads.
No confirmed completion dates have been announced for Buildings 2 or 4, and future tenant announcements will determine what the next phase of the park brings to the I-75 corridor.